Washington Supreme Court invalidates one-year contractual limitation period for lawsuits under residential construction contract.

November 7, 2022 • William A. Young

In a 5-4 decision, the Washington Supreme Court held that a one-year limitation period to file a lawsuit under a residential construction contract was “substantively unconscionable and, therefore, void and unenforceable.”

In Tadych v. Noble Ridge Construction, Inc., et al., No. 100049-9 (Wash. Oct. 27, 2022), the Tadychs entered into a written contract with Noble Ridge Construction, Inc. (Noble Ridge) to build their custom home. The contract, which was drafted by Noble Ridge, included a warranty provision that provided, in pertinent part:

Any claim or cause of action arising under this Agreement, including under this warranty, must be filed in a court of competent jurisdiction within one year (or any longer period stated in any written warranty provided by the Contractor) from the date of Owner’s first occupancy of the Project or the date of completion as defined above, whichever comes first.

The Tadychs had approximately one month to review the contract before signing it, and apparently did so without objection to the warranty provision or the limitation period.

Noble Ridge completed the home, and in April 2014 the Tadychs moved in. Around 10 months after taking occupancy, the Tadychs claimed they discovered construction defects, engaged a construction expert, and notified Noble Ridge of the same. However, the Tadychs did not file a lawsuit against Noble Ridge within the one-year period.

Discussions between the Tadychs and Noble Ridge regarding the issues they identified in early 2015 ended in early 2017 without resolution. The Tadychs then sued Noble Ridge in late 2017, more than three years after taking occupancy. Their claims were dismissed on summary judgment under the warranty provision, which was affirmed by the Court of Appeals.

The Washington Supreme Court reversed the trial court and Court of Appeals and remanded the case for trial, holding that the one-year limitation period was unenforceable because it is unconscionable. Although the Court briefly acknowledged that parties are generally held to the terms of their contracts, the Court’s analysis quickly transitioned to consideration of whether the warranty provision was unconscionable in light of the six-year statute of repose under RCW 4.16.310.

RCW 4.16.310 provides that a claimant has up to six years to file a lawsuit for claims arising under a construction contract. Prior to the Tadych opinion, Washington courts recognized that parties may contract for a shorter period. E.g., Washington State Major League Baseball Stadium Pub. Facilities Dist. v. Huber, Hunt & Nichols-Kiewit Constr. Co., 176 Wn.2d 502, 512-13 (2013) (“[S]ubject to the same principles that apply to contractual modification of a statute of limitations, parties may agree to set the time for accrual of causes of action arising under their construction contracts, and may do so with regard to both the statute of limitations and the statute of repose.”).

Under the facts of this case, however, the Court held the limitation period in the North Ridge-Tadych contract was unenforceable because:

[T]his limitation period effectively abolishes a plaintiff’s statutory right under RCW 4.16.310 to bring a claim. Here, the Tadychs filed suit within three years of discovering some of the contractor’s defective work. Under chapter 4.16 RCW, the suit is timely. The one-year limitation provision provides a substantially shorter limitations period than plaintiffs are otherwise entitled to under RCW 4.16.310 and benefits the contractor at the expense of the rights of the homeowner.

The Court further held that the provision was unenforceable because “it eliminates otherwise established statutory rights and is one sided, benefitting the contract drafter [Noble Ridge], is also not prominently set out in the contract, is not negotiated or bargained for, and provides no benefit to the affected party.” Therefore, the one-year limitation for lawsuits under the contract was invalidated, and the Tadychs could proceed to trial on their claims.

Chief Justice Gonzalez wrote the dissenting opinion, which argued that the warranty language was not unconscionable because: “f the defects had been discovered after the contractual limitations period had run, the contract might have been substantively unconscionable. But given that the Tadychs discovered the defects before the contractual limitations period lapsed, the fact that they lost the protection of the discovery rule is irrelevant and not a ground to find the term substantively unconscionable.”

Further, the dissenting opinion argued that the contract was not procedurally unconscionable because “[t]he limitations clause was plain in the contract” and “[t]he Tadychs had a meaningful opportunity to review the contract—a month—before signing. All the terms were in the 14-page contract, and the Tadychs had ample time to consult counsel. … These facts do not support a finding that the one-year limitation on suits was procedurally unconscionable.”
Nevertheless, the majority opinion controls. Under Tadych, if a contractual claims limitation provision “eliminates otherwise established statutory rights and is one sided, benefitting the contract drafter, is also not prominently set out in the contract, is not negotiated or bargained for, and provides no benefit to the affected party,” it may not be enforceable.

Going forward, contracting parties should pay special attention to claims limitation language in their contracts to ensure risks are allocated consistent with current Washington law. For contracts that include claims limitation provisions, these provisions may still be enforceable if thoughtfully drafted to address the unconscionability factors discussed in Tadych. Contract drafters may consider making the language more prominent (e.g., in bold and large font), adding specific acknowledgements and space for the parties to initial to confirm that it has been reviewed and bargained for, and increasing the limitation period. However, this does not guarantee such a provision would pass muster post Tadych, and contracting parties are encouraged to consult with counsel.

related tags

construction law

The information found on this website has been prepared by the law firm of Schlemlein Fick & Franklin and is for general informational purposes only. It is not intended to be and should not be considered legal advice or a legal opinion or a solicitation of legal business. Transmission of the information is not intended to create, and receipt does not constitute, an attorney-client relationship. Internet subscribers and online readers should not act upon any information contained on this website without seeking experienced professional counsel. The information contained in this website may or may not reflect the most current legal developments and should not be considered a substitute for obtaining legal advice from competent, independent, legal counsel concerning your particular factual situation, or any specific legal questions you may have. No attorney-client relationship attaches as a result of any exchange of information, including emails sent to the firm. Please do not send confidential information or sensitive materials via email until and only if an attorney engagement letter has been sent to you and signed by you and the lawyer.

William A. Young

Meet William

Mr. Young earned his undergraduate degree from the University of Washington in 2010 with a Bachelor of Science in Construction Management. Will worked as a project engineer and assistant project manager for a local general contractor for more than three years prior to (and during) law school, receiving his Juris Doctorate from the Seattle University School of Law in 2016. Will was admitted to the Washington State Bar in 2017, and his years of edu...